Undercorrelated WBS Elements Means Understated Cost Risk

May 9, 2009 @ Herding Cats from Glen B. Alleman

The current issue of the National Estimator, The Society of Cost Estimating and Analysis, monthly magazine has an eye opening article titled "Correlating Work Breakdown Structure Elements."

A Key aspect of cost risk is correlation between work breakdown structure (WBS) elements.

...

For example .. with a 30 element WBS has an assumed zero (0) correlation between all elements, but the actual correlation between WBS elements is 0.2, the total cost risk will be underestimated by 60%

This shoudl be a frightening fact for all of us who assume no correlation, or worse have no recognition that such correlations are important.

    So when the question of "why are projects late and over budget," is asked this is one of the answers, along with a myriad of other answers:

  • No understanding of the needed schedule margin, derived from Monte Carlo Simulations
  • No understanding of how the increasing maturity of the products or services are being measured in units meaningful to the stakeholders
  • No management of the inherent risks of the program
  • Insufficient partitioning of work efforts to reduce the coupling between work durations - "How Long Are You Willing to Wait Before You Find Out You're Late?"
  • The inability to determine the capacity for work, so all work estimates are underestimated.
  • And the final killer result - multitasking creates hidden correlation between WBS elements.

The last element alone, should be reason enough to start to understand the correlations, and remove the multitasking. After that the real correlations, need to be ferreted out and placed in the cost model.

   
 

Related Posts


This article is syndicated from A Girl's Guide to Project Management . The original article is available here. Read more in A Girl's Guide to Managing Projects, Project Management News .


Reminder : PMToolbox has ZERO tolerance to copyright violation and agrees to follow strictly PMI's Professional Responsibility. That's why each post on this site includes a link to the original version at its source site.

Comments

Got something to say?






Get Adobe Flash playerPlugin by wpburn.com wordpress themes
Project Management Resources | Project Management Templates | Project Management Books | Project Management Software

pmtoolbox.org is your one stop source for project management, project management software,project management books, project management templates, project management news, project management glossary,project management tools...