Improving Duration Estimates
December 25, 2007 from PMConnection
Three Point Estimates, PERT and Microsoft Project I have managed a project or two in my past. Some completed early, some right on time, and some completed well beyond the target date. But my latest project is different. I wanted to develop a schedule that was as accurate as possible with respect to the projects finish date. I knew that in order to do this right would require gathering effort estimates for each task. However, this organization is not quite ready for that. They are accustomed to giving only duration estimates. I did not have the time, energy or influence to change the culture and request effort estimates for each task. In the past, I worked with my team of subject matter experts to determine the various activities that must occur. As a group, we would then determine the sequence of those activities. When gathering the duration estimate for each task, I asked the subject matter experts for their estimate. They gave me one number for each task. The question I always had was, “how precise was this one number?” Did the person who gave me the estimated duration “pad” that estimate? In other words did they include extra time to allow for various uncertainties? Were all of the estimates padded? Which ones were padded and which ones were not? When reading my copy of PMBOK (the third edition) one night in bed, I stumbled into a section in Chapter 6 – Time Management about Activity Duration Estimating. One of the “Tools and Techniques” listed for developing a duration estimate was Three Point Estimates. It states that determining this estimate involves gathering three different estimates; Optimistic, Pessimistic, and Most Likely, and then averaging those three estimates (p. 142). Just before falling asleep, I thought: “This would be a better approach.” In the shower the next morning, I remembered a gentleman giving a presentation a few years ago at a local PMI meeting around PERT estimating. I ran to the office and pulled out my older version of PMBOK (2000 edition). I skimmed through it and found the section on PERT estimating. I found that PERT stands for Program Evaluation and Review Technique and it uses a weighted average to determine duration. (p. 75). I even found the formula: (Optimistic + 4 x Most Likely + Pessimistic)/6. I thought about this for a moment and came to the conclusion that the weighted PERT average duration estimate would be an even better approach than a simple average since it is putting more emphasis on the Most Likely outcome. The day progressed and I decided to load my tasks into Excel then ask the team members to give me their three different duration estimates. I could put those into three different columns and create the formula to derive the PERT estimate. I would then transfer this one number into the Duration for each task within MS Project. As I opened up my Microsoft Project schedule and began to extract the tasks into Excel I paused. I remember thinking; “Wouldn’t it be nice if I could somehow capture the three different estimates right here within Microsoft Project. Perhaps then I could look at an over-all Best Case (Optimistic), Worst Case (Pessimistic) and Most Likely schedule.” So I began to poke around the different options within Microsoft Project. Low and behold there IS an option for PERT Analysis!! If you click on >View, >Toolbars, >PERT Analysis, a fancy little toolbar will appear.
This article is syndicated from PMConnection
. The original article is available here. Read more in PMConnection, Project Management News .
Reminder : PMToolbox has ZERO tolerance to copyright violation and agrees to follow strictly PMI's Professional Responsibility. That's why each post on this site includes a link to the original version at its source site.
Comments
Got something to say?
COBIT
Microsoft Project
Open Source
CPI
Viewers and Companion Products
Education and Training
Hosted
Earned Value
pmi
communication
Management
PMO
Resources
Project Management Glossary
Project
MS Project
pmbok
Resource Management
WBS
lessons learned
EV
Scope
Training and Consulting
Project Management Office
people
Software
Risk Analysis
Project Schedule
associations
Schedule
Industry-Specific
EVM
pm
Program Management Office
Construction
process
Articles
Gantt
sharepoint
Project Management
ITIL
Estimating
Prince2
Project and Program Management
SPI