Agile Estimating: How long is an ideal day?
November 24, 2006 @ Agile Project Planning from David Churchville
About seven years ago, my first attempt at doing an estimate using agile terminology went something like this:
Me: "OK, I estimate this functionality at about 3 ideal weeks of effort"
Boss: "Uh...what is that in calendar time?"
Me: "Well, er, it's complicated, it depends on team velocity and planetary motion"
Boss: "Great, can you tell me by tomorrow?"
After doing some reading and thinking, I decided an ideal week was something like a "man-week", adjusting for daily distractions. For most people I've worked with, this adjustment factor (called a "load factor" in the original XP books...yikes) is somewhere between 0.5 and 0.7.
In fact, some studies suggest that the maximum productive time for most workers is five hours, regardless of how much time they spend in the office. Work that requires intense concentration, like say, software development, is more prone to productivity loss from distractions, phone calls, etc.
In other words, an ideal week for a single developer looks a lot like half of a "man-week". Looked at differently, a developer has a capacity (or velocity) of 0.5 ideal weeks per calendar week, or for a two-week iteration, about one week of ideal effort.
So a team of four developers of roughly equal capability would be able to implement about two ideal weeks worth of estimated effort in an iteration (of 2 weeks).
Another popular method of estimating agile user stories is to use a point system to measure the relative size. By using points, a team can estimate the size of a story relative to other user stories.
A 2-point story is twice as difficult to implement as a one point story, and a 4-point story is twice as hard again.
Personally, I tend to prefer the ideal time units, since it's easier to explain to customers, but I have heard reports that point systems have had good results as well after the initial confusion.
How do you estimate and why?
For more on agile tools and techniques: http://www.extremeplanner.com
(Tags: agile, project management)
This article is syndicated from Agile Project Planning
. The original article is available here. Read more in Agile Project Planning, Project Management News .
No tag for this post.
Reminder : PMToolbox has ZERO tolerance to copyright violation and agrees to follow strictly PMI's Professional Responsibility. That's why each post on this site includes a link to the original version at its source site.
Comments
Got something to say?
Software
Education and Training
CPI
EV
Viewers and Companion Products
Project Management Glossary
Open Source
associations
Articles
Prince2
lessons learned
Hosted
sharepoint
Management
COBIT
ITIL
communication
Estimating
process
pm
MS Project
Resources
EVM
Project and Program Management
Gantt
pmi
Industry-Specific
people
Risk Analysis
Program Management Office
Schedule
Project Management Office
Construction
SPI
pmbok
Microsoft Project
WBS
Project
Training and Consulting
Project Schedule
Earned Value
Scope
PMO
Project Management
Resource Management